Road Work in our Neighbourhood

roadwork

The City of Vancouver has scheduled water main work in our neighbourhood from April 5 - August 24. (Please note these dates are tentative and could be subject to change.) We are asking parents and caregivers to consider parking further away from the school and walking in. Seeing the weather is now getting warmer and dryer, it is a great reason to build those healthy habits and walk, bike or roll to school.

As part of the water main construction, street closures and parking will be impacted during crew’s typical work hours of 7:00AM – 3:30PM, Monday to Friday.

Sidewalk access on the east side of Bayswater St. will still be maintained during construction and secure fencing of the construction zone will be ensured.

SEGMENT
TENTATIVE STARTTENTATIVE FINISHWEEKS
W 8th Ave-Stephens St to Larch St
Wed., Apr. 5, 2023
Fri., May 5, 2023
4
W 8th Ave-Balaclava St. to Bayswater St
Mon., May 8, 2023
Thu., May 25, 2023
3
Balaclava St-W 8th
Fri., May 26, 2023
Mon., Jun 12, 2023
3
W 7th Av-Balaclava St to Bayswater St
Tue., Jun.13, 2023
Thu., Jun 29, 2023
3
W 6th Av-Balaclava St. to Bayswater St
Fri., June 30, 2023
Thu., Jul 20, 2023
3
Bayswater St-W 4th Av to W 8th Av
Fri., Jul 21, 2023
Thu., Aug 24, 2023
5
Total Est Duration

21